Lenovo Flex System Implementation Team
OZ
Ola Zaher
Infrastructure Section Head at Citystars Properties
Our deployment took nearly two days between hardware installation and the deployment itself of the VMware, as well as to finalize all our VMs. So it took about two days for deployment, all-in-all.
When we started the deployment of Lenovo Flex, we started with the hardware itself, then the switches, then the storage and the Lenovo tech library. We did almost one after another and finished within one day.
This was done by Kolaly. We had a good experience with them.
View full review »OZ
Ola Zaher
Infrastructure Section Head at Citystars Properties
A Lenovo partner did the implementation for us.
View full review »We do the implementation of the Lenovo Flex System.
View full review »Buyer's Guide
Blade Servers
March 2024
Find out what your peers are saying about Lenovo, Hewlett Packard Enterprise, Cisco and others in Blade Servers. Updated: March 2024.
765,234 professionals have used our research since 2012.
We used a third-party vendor for the implementation.
We had a team of 10 for the deployment of the support infrastructure.
View full review »Buyer's Guide
Blade Servers
March 2024
Find out what your peers are saying about Lenovo, Hewlett Packard Enterprise, Cisco and others in Blade Servers. Updated: March 2024.
765,234 professionals have used our research since 2012.