The solution should support Cisco or other vendor interconnect models. Our previous platform supported extenders and interconnects. 

A lower price model should be offered so customers at every level can use the solution. This would allow businesses to grow their data centers and be more competitive with Dell and Cisco. 

View full review »
Petr Student - PeerSpot reviewer
Senior Technical Architect at a tech services company with 10,001+ employees

The hardware is fine but OneView needs additional event management and filtering options.

Documentation could better describe the solution's configuration possibilities.

Sometimes there are firmware or software difficulties when connecting between networks or with storage. The solution is a hardware that is defined by its software so management issues can occur on servers or within the software running the hardware. For example, an electric car depends on its software. If the software is bad, then you can expect issues and problems that might not allow you to start the car. A technician might have uploaded the wrong code into firmware or a software developer might have make code mistakes and these things cause issues. The solution can only be as reliable as the software used to run it.

View full review »
JuanDuque - PeerSpot reviewer
Manager of Capacity and Control Management at a insurance company with 10,001+ employees

They must improve the OneView tools. They could put in more tools and improve options to help better manage more things and so we can integrate more platforms with OneView. Right now, Binware is integrated with some licenses to OneView, and you can integrate, Citrix licenses with OneView or RedHat, for example, with OneView. The improvement has to be introduced in order to activate more license options for other plots so you can control it with the OneView tools.

View full review »
Buyer's Guide
HPE Synergy
March 2024
Learn what your peers think about HPE Synergy. Get advice and tips from experienced pros sharing their opinions. Updated: March 2024.
768,740 professionals have used our research since 2012.
WH
Services Support Supervisor at State of Washington

For the storage modules, which can be put in a single frame, they currently can only be addressed to compute modules within the same frame. It would be nice to be able to use those to assign cross frame.

View full review »
EhabHosni - PeerSpot reviewer
HPE Solutions Manager at Summit Technology Solution

Using HPE Transporters instead of train switches would simplify network configuration by creating a flat network without zoning between servers and storage, fostering tighter integration.

View full review »
DL
Architect at Argos Limited

The post-sales activity needs improvement. There is some sort of convoluted spreadsheet that you have to fill in prior to the platform being delivered. It seems a little bit out-of-date and inefficient. Surely, there is some sort of web page configuration tool online that a customer could use. Then, it could be validated by somebody else, like a partner or HPE technical resource, then that would be a lot more efficient. A spreadsheet seems a bit out-of-date

View full review »
Manjunath V - PeerSpot reviewer
IT Operations Team Lead at a government with 10,001+ employees

This solution could be improved by increasing the speed on the conversion adapters. It should be 100 gigs. I would like to have bandwidth conversion on SBAs and ethernets to understand how much each physical server is consuming.

View full review »
Mohd Shadab - PeerSpot reviewer
Senior Information Technology Analyst at Tata Consultancy

There is an HP plugin we need to enable in vCenter for RMCV backups. Sometimes we observe that the data storing is not happening correctly. It's like that data store, whatever we have added in Synergy, takes a backup in a day. Sometimes we observe that the backup is not happening properly. We used to get alert emails that the backup was failing for the particular storage. In that case, we needed to do a restoration during that time. It would give us a lot of trouble to restore the VM from a particular backup.

There is no expertise. There is a lack of expertise at an acceptable level from the technical teams. We need very senior higher-level technical teams to come in in the future. 

It takes a lot of time to analyze the logs.

In the Generation 10 modules, we have observed that very often the server has hardware issues. We have to frequently contact the vendors. 

View full review »
TJ
System admin at Riyad Bank

The firmware, software, and driver levels must be improved. The product should be stabilized as soon as possible. Some hardware of the product was not in good condition. We faced some issues within six months. We requested HPE to replace them. The solution must concentrate on improving the product quality.

View full review »
RC
Manager IT Infrastructure at a aerospace/defense firm with 10,001+ employees

It has affected the productivity of our development team in a bad way. When we first stood the hardware up 18 months ago, the image streaming capacity and capability were not very good at all. We had hoped that it would allow us to be more composable and be able to switch over from one version of an operating system to another version of an operating system. However, it wasn't ready for prime time yet. Therefore, we had to go back to a deployment of bare metal install. We are still waiting and trying to figure out how we can do the composable infrastructure.

We are all about graphics. I know that the Synergy has a sidecar on it, so innovation into graphics capabilities and more broadly used storage. Right now, we have 180 blades and 15 frames, but our only solution for storage is either onboard the blade itself or some network-based storage. We could probably bring some Fibre Channel into play. However, we would maybe like to see some innovation around the storage and those systems.

It still has some room to grow. For our solution, we need something between the c7000 and Synergy. Synergy is the high-end deployment, and we're still learning to how to do the composable infrastructure, so we can turn it around and make it look like this today and that tomorrow. The c7000 gave us a stable workstation remodel. We went from an Acura to a Maserati, needing something in between.

View full review »
DEVINDRA SINGH CHAUHAN - PeerSpot reviewer
Data Engineering Manager (Big Data & Analytics) at NCR Corporation

There really isn't any valuable feature. Our team in Brazil does not want to change, and that is why it's still running there. They have not improved their product since it was purchased. I would like to see the product be compatible with Oracle invoicing or Salesforce invoicing.

HPE Synergy should be easier to use and integrate with other databases like Tableau and with the cloud. It is difficult to integrate with cloud-based data sets. I also would like to see better customization ability.

View full review »
Ayub Mohammed - PeerSpot reviewer
Solutions Architect at Ingram Micro

This is a product more suited to enterprises. It's not for small companies. 

The cost is quite high. 

View full review »
VB
Senior Engineer at Mannai

Over the two years of using HPE Synergy, we have found some hardware failures that are frequent in the SOP models, CNA cards, and converged network adapters. These failures are frequently happening for a lot of the customers.

View full review »
BB
VP Technology at Scalematrix

There is room for improvement in the setup.

View full review »
Getachew Zeleke - PeerSpot reviewer
Senior Custormer Engineer at Afcor PLC

HPE Synergy could improve its remote support.

View full review »
Ali Balandy - PeerSpot reviewer
Systems Architect at a educational organization with 1,001-5,000 employees

It's a pretty complex solution.

The continuous update of the firmware and the patch updates and security updates for the hardware make it continuously complex. It all comes back to complexity. I don't have any other concerns. It's all about how complex the component is.

View full review »
VL
Systems Engineer at a retailer with 1,001-5,000 employees

I would definitely like to see them fix the firmware updates on all the blades. No matter what operating system it is running on, make sure I can do the firmware as well as the software for those firmware components at the same time. I don't want to have to rely on an external product. Let's bring that product inside the menu so that I have a better experience with updates. Firmware is a very big thing.

I would also like them to bring management of all the Synergy equipment into a single management interface, no matter where they're located.

View full review »
VD
CIO at GCC

I'd like to see the firmware updates, as well as the built-in OneView and imager in Composer, become a little more powerful and faster.

I would expect that newer blades that would go in it would have newer processors and be faster. It's pretty flexible with storage. There are new solutions on the storage front, that are going into it as well. I expect that portfolio to increase, just like with the rest of the solutions they have.

Other than that, I think everything's great.

View full review »
RC
Systems Engineer at Scientific Games

I would like the ability to take the storage tray that is in a chassis and share it out to multiple chassis, not just the servers within the same chassis. This would be more efficient with resources.

View full review »
LA
Senior Executive Manager - Data Center Virtualization at a insurance company with 1,001-5,000 employees

There is always room for improvement.

Based on our use cases, I don't believe there are any additional features required.

View full review »
Marziyeh Bahrami - PeerSpot reviewer
Project Manager at AHS

In terms of additional features, there is nothing that I would add. However, the pricing can be improved as it is a costly solution due to sanctions in Iran. When we buy an HP service or system, we need a company in China to purchase it and send it to Iran. This gets very expensive as it takes time to complete this, and by the time we receive the product, the HP or Cisco company says it's the end of the sale, and there is a new version. The limitations and sanctions are very harmful to Iranian IT specialists.

View full review »
KI
Manager at a financial services firm with 1,001-5,000 employees

Having a seamless DR implementation would help significantly.

There is room for improvement to OneView.

View full review »
Ahmed Aboauf - PeerSpot reviewer
Service Delivery Manager at iSky Development

I find the product documentation to be disorganized; it's not intuitive and the info required for checking a specific step-by-step configuration is buried under too much literature. This could be a more robust solution with an effective internal storage portfolio for the servers. If they were to provide an end-to-end NDM product, that would be much better.

View full review »
JW
Manager Engineering Services at a manufacturing company with 1,001-5,000 employees

The biggest problem that I have with it is the speed of setup.

View full review »
ML
Service Manager at a financial services firm with 10,001+ employees

I am rating this solution an eight (out of ten) because it is really good. However, you can always improve some things.

View full review »
CS
Technical Consultant at a manufacturing company with 1,001-5,000 employees

It would be nice if the OneView umbrella could truly be one view and cover everything. Synergy has its own version of OneView. ProLiant Servers have their own version of OneView, so it truly isn't one view. We also have other platforms within HPE that aren't covered by OneView at all. We have many views instead of one view, and it would be nice if that could be resolved. That would help us a lot.

The timeliness of updates, firmware, and things of that nature needs improvement, as far as what we have to apply, and when, being able to maintain a consistent load on each one of our frames.

View full review »
it_user685020 - PeerSpot reviewer
Chief Infrastructure Architect at a transportation company with 10,001+ employees

One of the things that I would like to see, and could be in their road map, is getting virtual connect to 100 Gig throughput.

What they're coming out with initially on the road map is a 40 Gig up-link on virtual connect. That would be one of the things that we'd like. Other things that would be useful for us would be adding an AMD CPU to their product line in the 2018 time-frame.

View full review »
PL
Advisor System Administrator at a computer software company with 501-1,000 employees

A faster Composer module would be a good inclusion for the next release of this solution.

I would like to see an increased variety of uplink options in the Virtual Connects.

The inclusion of these features would allow us to more easily grow our network infrastructure and accommodate future growth.

There are improvements that can be made in the area of OneView integrations and firmware, with respect to how the proper firmware versions are matched to the OneView installation that you have. 

View full review »
JN
Senior Server Engineer at a tech services company with 5,001-10,000 employees

I would like the ability to have my storage components accessed from any other frame across the backplane. If we have a storage module and we run out of space in that frame, it'd be nice to be able to share it across the frames. You can do it with hyperconverged. Why can't you do it with Synergy?

View full review »
LM
System Architect at a tech vendor with 201-500 employees

The speed in OneView and how it updates the entire configuration needs improvement. If they can do that, and it could be a little more clear on what impact different actions will have for certain things, that would be good. They do give warnings for certain things, but there are other things where they don't really give you a warning, then you do it and it will be rebooting something like the host (or whatever). If that is in a production environment, that is really dangerous. This is our pain point.

View full review »
WA
SVP Data Technology at a marketing services firm with 51-200 employees

I would like it to connect to the HPE Cloud Connect compute platform for simplicity of our infrastructure.

Our IT infrastructure costs have gone up each year by 20 percent.

View full review »
JohnDeavers - PeerSpot reviewer
Senior Solutions Architect at ePlus Technology

Gen 11 is being released. That's going to have a lot of advantages over Gen 10 and previous generations in terms of the cooling modules in the servers to keep them cooler and run with more efficiency and better performance. There are more management features with iLO 6 and the latest OneView management.

In terms of additional features, I've been requesting SimpliVity to be running on a compute module versus a 1U and 2U.

View full review »
MI
System Engineer at Blue Shield of California

A big thing for me is moving InfoSight for ProLiant into OneView, or at least connecting it. Today we have to use the iLO Amplifier Pack and that would require us to reconfigure iLO on every single one of the servers, independently, to get that data into InfoSight. We're really looking for a single control and management plane.

Also, Fibre Channel support within the Virtual Connect modules is lagging behind on the speed and the connections and configuration.

View full review »
HB
Senior Infrastructure Engineer at a retailer with 1,001-5,000 employees

I would be more comfortable if Ansible actually rolled back the data used for automating platforms. If it could be communicated to the upstream Ansible, I wouldn't need to go back and forth and validate the libraries as we upgrade the Ansible version. The backward compatibility is there, but if we need to spend time testing the code frequently, it will make our lives difficult, and we might lose some production cycles.

View full review »
MR
Network Specialist at Roswell Park Cancer Institute

The setup experience needed some improvement.

View full review »
VH
CIO at La Huerta

I would like more storage with this solution, because we still need 3PAR or other storage outside the box for the amount of data that we have.

View full review »
it_user683241 - PeerSpot reviewer
Infrastructure Architect at FMOLHS

In the future for Synergy, we would like to see SaaS connectivity and sharing of storage between frames.

View full review »
LL
System Engineer at a manufacturing company with 1,001-5,000 employees

The vendor needs to focus on the features that are already included and make them better.

The installation and initial setup process is complex and needs to be improved.

View full review »
JP
Storage Engineer at Brigham Young University

If it would be possible to connect clusters of five with other clusters, so that they could all share resources, that would change the game for us. It would make it a viable solution for us.

There is room for improvement with support. That's a big one because of the struggle we had getting the technical expertise which we needed. Improving support is hard to do. It's a global company. They've got disparate teams with disparate specialties all over the place and it's a very new product. So we tried to take all that into account when we were evaluating. In the end, before you push a product out, your support has to know how it works and how to support it.

View full review »
AB
Cloud Architecht at a wholesaler/distributor with 1,001-5,000 employees

Synergy could probably do some code enhancements to simplify the deployment a bit more. However, it is still a great deployment methodology overall.

View full review »
AH
Information Technology System Administrator at a energy/utilities company with 10,001+ employees

Its management interface needs some work. It is not the best in terms of management. It has decent management. Its user interface can also be better.

View full review »
RA
Storage & Backup Engineer at a government with 10,001+ employees

ICMs could be better in this model. When you look at its competitors, the most critical point is the throughput. HPE is the best with the ICM module, which is an interconnect module that connects the servers of the frames to the LAN and SAN. 

HPE Synergy should also support the latest processors provided by Intel.

View full review »
Alexander Lavrinovich - PeerSpot reviewer
IT consultant at Soeldner consult gmbh

Maybe two years before, there were issues with drivers. However, the issues were always fixed quickly.

They were not so deep into integration with VMware. As a partner of VMware, I'm focused more on VMware products and I don't remember many details about HPE now that time has passed. However, there should be more integration. 

View full review »
SA
Data Center Implementation Engineer at a construction company with 11-50 employees

The connectivity needs to be improved. The compatibility with old infrastructure and networking should be better than what it is now. The networking part is very complex. It should be simplified.

The setup was a bit complex.

They need to make it easier for firmware upgrades. The virtual connection is very complex and they need to make it easier. 

The storage configuration should be improved. When we are connecting the 3PAR storage to Synergy, I have to manually add the values again when what should be happening is, when I'm connecting, when I'm assigning, the storage should be automatically allocated.

View full review »
AJ
CEO with 51-200 employees

They actually have a different offering with Nutanix. That's more generic. The Synergy platform is HPE-specific and more for on-premises. You're kind of locked in with VMware and the HPE with the VMs. The Nutanix offering is a bit more flexible.

View full review »
SM
Director of Infrastructure at Alliant Cooperative Data Solutions

I would like to see more nodes in a single chassis so we wouldn't have to purchase additional chassis.

View full review »
BF
Senior Systems Engenier at a healthcare company with 501-1,000 employees

Stability when you upgrade needs improvement.

View full review »
it_user680295 - PeerSpot reviewer
Chief Technology Officer at vGRID New Zealand

We'd like to see faster networking in the back-end. I'm not saying it's slow at the moment, but we would just like more speed from a future-proofing point of view. We are seeing 25 Gig capability in our switch fabric so extending that to Synergy compute nodes makes sense. I guess it is a natural progression that is coming to the Synergy platform as well.

View full review »
EG
Sales Engineer at a tech company with 10,001+ employees

The whole point of Synergy is, you're going to have this central management. You're going to have the composer where you can build stuff, and a lot of it's built on OneView. I think they're using the same code, but they've done something different to it to make it easier to use. That means you're managing and you're monitoring your networking, your compute, your storage from it, but not everything works. If you have got Virtual Connect, that can be managed and monitored. You put in a Brocade switch; you can't as there's a limitation. 

Also, the storage, the JBODs. Unless you're using VSA, I think it's tied to the frame that you're in.

View full review »
LC
VMware Administrator at a energy/utilities company with 1,001-5,000 employees

One of the features I want to see, which I will see with OneView 5.0, is to have all the OneView consoles in a single pane of glass. That will make it easy to see everything in one place and not have to log in to multiple consoles.

View full review »
PB
Director at a tech company with 10,001+ employees

It has been in the external integrations to other platforms that we have, which aren't HPE, where some of our challenges have been. We are still working on these.

I would like to see some integrations with non-HPE platforms. The Synergy platform is working pretty well in most cases. It does what it is advertised to do. Integrating it into our larger environment that is not HPE products has been somewhat of our challenge. I would challenge HPE to go fix and address these gaps. Have a story there, because not everybody will run HPE throughout their entire data center. I have other suppliers in there, and they have to work together.

What we are observing is to upgrade a whole rack of Synergy, so four frames when it's fully loaded, we are spending about 50 human hours doing that. There is a lot of work time and wait time in there. Overall, this work effort is spread across a bunch of people and the total time is about 50 hours. I don't know what percent increase that necessarily is, but it is a lot of work that we didn't do before. So, it feels like a big increase. That is still us rationalizing how the platform should be maintained.

I would like something that makes it even easier for developers to leverage OneView. It is all API driven. However, if you are using the web GUI that is OneView, you can't get any feedback about, "If I click this button, that button, or that button, before I hit go..." Show me what the API call is. Help me develop code faster if I am not a developer who wants to go read the whole API guide. Help me point, click, and start to develop code incrementally.

View full review »
ZA
IT Infrastructure at a real estate/law firm with 1,001-5,000 employees

The performance could be better. The converged network cards initially didn't work. However, later on in the newer version, they came up with 50 GB network cards to replace the 20 GB ones, and it's perfectly fine now. At times, it could also be more stable.

View full review »
David Fartouk - PeerSpot reviewer
CTO at a tech services company with 11-50 employees

I've found the user experience to not be that great. It's something that they could really improve on. They need to make it more user-friendly.

The profiles aren't so easy to work with.

We find the agility to be lacking.  

View full review »
TN
Information Specialist at a government with 5,001-10,000 employees

There are some functions which are not clear cut.

Instead of having Synergy vertical, make it horizontal. It is easier to stick in when it is vertical.

View full review »
MS
Server Architect at a financial services firm with 1,001-5,000 employees

I would like a longer amount of data for bandwidth utilization on Ethernet ports inside, as well as uplinks. The amount of data stored on them is way too small.

View full review »
it_user784080 - PeerSpot reviewer
Senior Hardware Engineer

It is hard to say because we have not fully implemented it yet.

One of the issues that we that we have been having is with the firmware baselining. So, we need to just making sure that we get that working. However, we are in the early stages. It may well be that we just tweak a few things, then it does everything for us.

View full review »
it_user781113 - PeerSpot reviewer
Solutions Engineer at Data Strategy

I'm very curious to see what comes with 4.0.

The big thing will be streamlining the Image Streamer process for deployment. The actual frame itself - Composer, OneView, all that - works fantastic. The more granular permissions that I know are coming are great. That answered a lot of our big questions and big customer demand. 

Now it's about the flexibility and the simplicity of using the product day to day and getting new features stood up as customer demands come forward. I'm not sure exactly what I want next but I'm looking forward to seeing what's next.

View full review »
it_user784098 - PeerSpot reviewer
IT Architect at Unibase

What I would like to see is a little bit more of architecture-oriented advertising campaigns or events for customers; not on the product itself, but more on the way they advertise products. They are too focused on the features. This is okay, but sometimes what I see that people lack is, "Okay, I understood the features, but how can I use this in practical terms? How can I put my Oracle in there? How can I use it for a VDI? Can I architect a huge SQL cluster with it, and what would be the best way to do that?"

I think that the documentation says that, but I don't see any events. I don't see any advertising in those terms.

In the end, it's more like they are giving the components, but they are not showing what you can do with the components. You can see you have all this, but what can I do from this? Can I make a cake out of it, or I can do an omelet? I can, but how? That's the missing link. They need to give me some ideas on how I can use this in such a way that I achieve my goals. This is the only thing that I really think the product lacks, a little bit more consumer-focused mindset. 

When you are talking about the product, talking only about features is good for me, for the partner, because I understand how to use the features to make the cake, but they don't.

View full review »
it_user685002 - PeerSpot reviewer
Leads IT Architect at a manufacturing company with 10,001+ employees
  • The newer and faster Intel line of CPUs that are coming in GEN 10
  • The software

OneView software is quite new and that will cause some improvements. Once we have it completely set up with the automation part, it will certainly help us in getting towards our vision.

View full review »
MK
CEO at DUKSCO SARL

As concerns room for improvement, the number of levers in the system should be addressed. Technical solutions should be made easier. The advice I would give is that HPE Synergy increase the availability of the deployment. 

View full review »
JS
Systems Administrator at a energy/utilities company with 201-500 employees

I would really like a way to validate the firmware in my specific environment before trying to deploy it. Those were the issues we had early on with firmware upgrades, particularly around certificates. All in all, having some level of confidence aside from it just having been tested generically would help. Something more specific to my environment would be very helpful.

There is room for improvement in the speed; that would be the biggest thing. The time to deploy firmware... Everything takes a really long time. Having that all sped up would be nice. The 4.2 firmware release has helped tremendously with that. From my side, I see about a 30 percent improvement in speed already.

View full review »
DH
Architect at a tech services company with 11-50 employees

Continue the playbooks with the automation integrations. More of that would be good, as it has been great so far. 

I would really like to see the type of hardware add-on operationalization made simpler in some way. How do I have a chassis and add in a second or third chassis, but not have to be so aware that it is number 11 versus number 12 within the frame? If they can address that, it would be a home run.

Continue the path of integrating OneView into a single product. A lot of different people have different OneView experiences based on which product they have used it for.

View full review »
it_user683274 - PeerSpot reviewer
Systems Programmer II at a transportation company with 1,001-5,000 employees

Firmware. I'd get the firmware to be a little more secure and a little more streamlined.

View full review »
it_user784032 - PeerSpot reviewer
Service Manager at Tenne

The deployment time of a system through OneView is pretty slow, but apparently that's being addressed in an upcoming update.

View full review »
it_user683229 - PeerSpot reviewer
Senior Systems Administrator at a manufacturing company with 1,001-5,000 employees

Now that we have the new generation, the G10, we have the security. That was one part that was missing. That is going to be important, because we will be running on Generation 9.

View full review »
KR
CEO at a tech company with 1-10 employees

I would just like it to work.

View full review »
DV
Delivery Manager at Harlan Italia

I think that they can improve the update because the update is problematic now. When you want to update the firmware, or when you want to update software on Composer, it takes a lot of time. A lot. For compute node, you need one hour for upgrading firmware. I think that is a big problem.

View full review »
it_user683247 - PeerSpot reviewer
Solution Architect at One enterprise solutions

I would like to see support for other vendors’ hardware.

View full review »
MH
IT Infrastructure Architect at a tech vendor with 10,001+ employees

I would like them to work more on the templates, targeting it to a larger scale organization which has to run 24/7. Maybe they can try to get that workload to target certain parts of an application that has to be on 24/7. The common example that we keep getting is with our animators. They have one template which is dedicated to their resources, and in the night, it does rendering. However, when we have stuff which is running 24/7, it's not really something that applies. So, maybe they can try finding more applicable use cases.

The solution has affected the productivity our deployment a little, but it has just been the normal getting used to the new system. I think once they get used to it, it will be fine.

View full review »
it_user567912 - PeerSpot reviewer
Owner and CEO at Bitcon

With the changing IT demands, they need to change more often and faster. We need applications to model tomorrow’s needs. We need more applications for changing users. There is a need for a more optimized infrastructure.

For instance, I have a customer with 20 blade enclosures. In those 20 blade enclosures, there are 40 management modules that you need to update and manage.

In troubleshooting, you have to determine if the issue is in one, two, or in all 20 modules. The diagnosis is harder.

With Synergy, we only have two management modules instead of 40. It's an efficiency thing that needs to be improved.

We'll see what will come next. We will probably see other types of enclosures, smaller or larger ones, and more options on the storage and networking side. This is the typical evolution of IT to go to more and faster.

View full review »
it_user685017 - PeerSpot reviewer
Solution Architect with 51-200 employees

It's a lot more about some of the speeds and feeds, such as the 25, 50, 100 GB virtual connections. In addition, I would like to see improvement in the 32 GB fiber channel connection at the end of it.

View full review »
ST
Senior System Engineer at a tech services company with 1,001-5,000 employees

It would be nice if the updates were not accompanied by downtime. We have encountered this issue at times over the years. 

The solution should come with external storage connectivity.

Owing to these minor issues, I choose to rate the solution as a nine out of ten. 

View full review »
OK
System Integration Engineer at a computer software company with 1-10 employees

In the past, I have had issues with configurations.

View full review »
MS
Chief Technical Officer at a tech services company with 201-500 employees

I think the main issue with Synergy is a topology that HPE defines to connecting and creating a cluster. There are satellites and interconnecting modules which should interconnect with one special topology. If you want to change that and add another shelf in the cluster you have to change everything. I think it's very, very complex. But for example, in UCS, you have fabric interconnects, USC blades connect to fabric interconnects. It allows you to add more and more USC blades to the fabric interconnect. There is no connectivity between blades chassis. In Synergy, there are many connections between the blades chassis and I think that's the main issue. The other thing is that Synergy has a composer module that OneView runs on and which manages that cluster. I don't like HPE softwares. I think, for example, in comparison, the UCS manager is the better solution for managed blades than OneView. OneView is not as strong for that

It would be helpful if Synergy would add Cisco networking products, and network models in CSG, C 7000, maybe Blade models, software Cisco products, for example, b 22, CISCO B22 modules. I think the number of customers that use Cisco in their data centers is more than the customers that use HPE solutions. Because of that, I think HPE should add Cisco products and network modules to Synergy - I think that would be a good idea. 

View full review »
Rami.chiha - PeerSpot reviewer
Principal Systems & Storage Engineer at a tech company with 51-200 employees

The OneView has improved a lot throughout the years with the release of the Synergy and OneView version 4, although it still has issues. The stability and smoothness of firmware upgrades for the compute modules can be improved by enabling full composability of the Synergy Frame.

View full review »
it_user783993 - PeerSpot reviewer
IT Admin at a financial services firm with 51-200 employees

From what I've seen, it's got pretty much what I think we need. Maybe after a little usage I can come up with new ideas, but right now it seems okay.

The possibility of using storage directly in the frame in order to have bigger storage directly there, and not having an attached storage like SAN or NAS. That would be helpful.

View full review »
SP
Storage and System Administrator in IT Operations Department at Puzzel | Solving Customer Interactions

The user interface could be more user-friendly. It's for admins, and you should have the knowledge to use it.

View full review »
it_user783930 - PeerSpot reviewer
IT Technology Team Lead at a tech company with 10,001+ employees

I don't know because this was the first time I've seen this product and I'm not very familiar with it. I need some time to work on it, to play with it.

View full review »
it_user783915 - PeerSpot reviewer
Network Administrator

When templates are created, there are some steps where you need to reboot the machines. Being in production, this is not a good idea. For example, if you reconfigure the network, you should not have to reboot the machine. You should just apply the new template and that's it.

View full review »
it_user783954 - PeerSpot reviewer
Server Technician

We just started. Because we're using 2012, we're having issues making templates and such.

We're having issues with the install process, and integrating our installation with the new technology.

View full review »
it_user191142 - PeerSpot reviewer
Gerente de Ingeniería Pre Venta at a tech services company with 11-50 employees

I would like to see better integration with other products.

View full review »
Buyer's Guide
HPE Synergy
March 2024
Learn what your peers think about HPE Synergy. Get advice and tips from experienced pros sharing their opinions. Updated: March 2024.
768,740 professionals have used our research since 2012.